19 open tasks across the team1 over 80% of budget

View: Mine·Team
Scope: Open·Complete·All
Team work
Sorted by due date. Click a task to see time entries + edit; click the client / project for their pages.
TaskClientProjectLoggedBudgetDue
360works email pluginFitzroy Basin Association (FBA)0m1h (0%)
Activities; Target Measures; Budget LinesFitzroy Basin Association (FBA)Flexmonster implementation5h
Additional Development 2022Fitzroy Basin Association (FBA)0m20h (0%)
Contact Join; Events; AttendanceFitzroy Basin Association (FBA)Flexmonster implementation21h28h (75%)
Feature RequestsFitzroy Basin Association (FBA)General Support 202245m
General SupportFitzroy Basin Association (FBA)General Support 20216h
Implement a visual calendar module into CRM moduleFitzroy Basin Association (FBA)Implement Calendar module in LINK5h16h (31%)
Indigenous reportsFitzroy Basin Association (FBA)General support16h 30m
Install and setup Filemaker Server 2024Fitzroy Basin Association (FBA)Server upgrade 20244h 30m
Mail-out module upgradeFitzroy Basin Association (FBA)0m32h (0%)
Modifications to Communications ModuleFitzroy Basin Association (FBA)0m28h (0%)
Modifications to CRM moduleFitzroy Basin Association (FBA)0m14h (0%)
NRM Plan (CQSS2030) IntegrationFitzroy Basin Association (FBA)NRM Plan Development6h50h (12%)
Phone supportFitzroy Basin Association (FBA)0m
Preliminary Discussion and AccessFitzroy Basin Association (FBA)Server upgrade 202430m
Project; Budget LineFitzroy Basin Association (FBA)Flexmonster implementation2h
SendGrid SubscriptionFitzroy Basin Association (FBA)0m12h (0%)
To Do ReportsFitzroy Basin Association (FBA)Flexmonster implementation31h 15m24h (130%)